Paver Calculator

Free calculator with worked examples, a paver size chart and a full materials list. Last updated October 2026.

This paver calculator works out how many pavers a patio, walkway or driveway needs, plus the gravel base, bedding sand, polymeric sand and edge restraint that go with them. People also look for it as a patio paver calculator. Enter the area, pick a paver size and a laying pattern, and get the pavers to buy with the extra for cuts already added, worked out by pattern. It also tells you how deep to dig and how much dirt comes out. This free calculator needs no sign-up and no email.

Quick answer: A 12 × 10 ft patio in 6 × 9 in pavers needs 320 pavers exactly. With 10% extra for cuts on a straight pattern, buy 352 pavers. The same patio needs about 1.63 cubic yards of base gravel (4 in deep, compaction extra included) and about 0.41 cubic yards of bedding sand.
Table of Contents

Paver Calculator

Base, sand and digging

Guide: a patio or walkway base is 4 to 6 in deep, a driveway base 8 to 12 in. The box is set for you; change it if your soil or local guidance says otherwise. Bedding sand is a 1 in layer, already counted below.

Joints, edging and price

Per sq ft pricing multiplies by the area you buy (with the extra added).

The waste percentages are planning guides from installer practice, not guarantees. Confirm with your supplier before you order. If your paver lists a coverage per sq ft, type it into the maker’s coverage box and the calculator uses that figure instead of the plain face maths.

Prices are optional: fill in a price only if you want a paver cost. Only the pavers are priced; base, sand and edging are extra.

Call 811 before you dig anywhere in the US: the free service marks underground utility lines on your lot. Base depths on this page are planning guides. For a driveway or anything that carries heavy loads, confirm the base depth and drainage with local guidance or a contractor, and on clay or wet soil expect to dig a deeper base.

Turning these numbers into a customer quote? Our free Estimate Maker has this same paver calculator inside, so the paver count goes straight into your estimate.

How We Calculate

This is the exact method the calculator above uses, step by step, so you can check any answer by hand:

Step 1: The area. For a rectangle, multiply the length by the width: 12 × 10 ft = 120 sq ft. For a circle, halve the diameter to get the radius, then multiply radius × radius × 3.1416: a 10 ft circle is 5 × 5 × 3.1416 = 78.54 sq ft.

Step 2: Pavers per square foot. Divide 144 (the square inches in a square foot) by the face of one paver. A 6 × 9 in paver has a 54 sq in face, so 144 ÷ 54 = 2.667 pavers per sq ft. If your paver or its pallet lists its own coverage per sq ft, the calculator uses that figure instead, because the maker’s figure already allows for the joint width they plan on. Makers list the coverage of the same paver both above and below the plain face maths, so there is no single joint percentage that fits every paver.

Step 3: The count, with the extra added in two steps. First the exact count is rounded up to a whole paver. Then the extra percentage for your pattern is added, and the answer is rounded up again. So 120 sq ft × 2.667 = 320 pavers exactly, and 320 with 10% extra is 352 to buy. This two-step rounding is why the buy count is always a little above the exact count.

Step 4: Base and sand volumes. Multiply the area by the depth and divide by 27 to get cubic yards, then add the compaction extra, because loose gravel and sand settle down when they are compacted. A 120 sq ft patio with a 4 in base is 120 × 4 ÷ 12 = 40 cu ft = 1.48 cubic yards, and 1.63 cubic yards with 10% extra for compaction. The 1 in bedding sand layer is 0.37 cubic yards, or 0.41 with the same extra.

Step 5: Polymeric sand bags. Divide the area by the coverage printed on your bag, and round up. Bag coverage changes a lot with joint width, which is why the calculator asks you for the figure on your own label instead of printing one fixed number.

Step 6: Edge restraint. The edging runs around the open edges: the perimeter of a rectangle is 2 × (length + width), and of a circle it is 3.1416 × the diameter. Spikes are worked out from your spacing: perimeter in inches ÷ spacing, rounded up.

Step 7: The digging. Dig depth = base depth + 1 in of bedding sand + the paver thickness. The dirt to come out is the area × the dig depth.

Every figure in the calculator, the worked example and the tables on this page uses this same maths at full precision. Rounding happens only at the final count, never in the middle.

Paver Sizes and Coverage

Pavers are sold by their nominal face size, the size of the top face including its share of the joint. Count with the nominal size, not with a tape measure on one paver, or the count comes out wrong. The chart below is plain face maths with no joint taken off, and the per 100 sq ft column is rounded up to whole pavers, the way you would buy them:

Paver sizePavers per sq ftPavers per 100 sq ft
4 × 8 in4.5450
6 × 6 in4400
6 × 9 in2.67267
8 × 8 in2.25225
12 × 12 in1100
12 × 18 in0.6767
16 × 16 in0.5657
24 × 24 in0.2525

That is why the 16 × 16 in row shows 57 per 100 sq ft: the exact figure is 56.25, and a part paver cannot be bought. The 4 × 8 in paver is the old standard size, sometimes called a Holland paver. Mutual Materials lists its Holland paver, this same 4 × 8 in size, at 4.63 per sq ft (one paver covers 0.215 sq ft), more than the plain face maths in the chart, because their coverage figure allows for a small joint. Counts from different makers can sit either side of the chart, which is why the calculator has a maker’s coverage box: if your paver lists a coverage, use it. Check the pallet’s coverage on the product page.

Thickness does not change the count. Patio pavers are usually about 2-3/8 in (60 mm) thick, and driveway pavers are thicker, but the face is what covers the ground. Thickness matters for the dig depth and for strength, not for how many pavers you need.

Working in metric, the standard paver is 200 × 100 mm, which is 50 pavers per sq m. A 10 sq m patio takes 500 pavers exactly, or 550 with 10% extra.

Extra for Cuts: Waste by Pattern

Pavers get cut at the edges of the job, and the pattern decides how much cutting there is. A straight pattern runs in long rows and wastes the least. Herringbone and diagonal work cuts on every edge. Curves and circles cut the most. These are the guide figures the calculator sets for you; every one of them is a planning guide, not a promise, so confirm with your supplier, and change the percentage in the calculator whenever you like:

Laying patternGuide extraBasis
Straight / running bond10%About 5 to 10%; never plan below 5%
Herringbone or diagonal15%About 12 to 15%; complex 45 degree work can run to 20%
Curved edges15 to 20%Our planning guide: about 15% for gentle curves, 20% for tight ones
Full circle20%Our planning guide: every paver on the rim is cut, so the top guide applies

The difference is real money. A 10 × 10 ft patio in 4 × 8 in pavers takes 450 pavers exactly. At the straight guide of 10% you buy 495; at herringbone 15% you buy 518; at the circle guide of 20% you buy 540. When you pick the circle shape in the calculator, the waste box is set to 20% for you, because a full circle cuts like the last row of the table. It stays editable.

Base Gravel and Bedding Sand

Pavers are only as good as what is under them. The standard build-up is a compacted gravel base, a thin layer of bedding sand on top of it, and then the pavers. The layers look like this:

Cross-section of a paver patio: pavers on 1 inch of bedding sand on a compacted gravel base, held in place by edge restraint Paver, about 2-3/8 in Bedding sand, 1 in Compacted gravel base, 4 to 12 in by use Subgrade (your soil) Edge restraint with spike Side view of the layers, not to scale. Depths are in the table below.

Base depth is set by the use, the soil and the climate. The industry guide (Tech Spec 2 from the CMHA, the association that took over from the ICPI) sets the minimum compacted base at 4 in for patios and walkways on well-drained soil, and at least 6 in for a residential driveway. Makers and installer guides go deeper than the minimums: Belgard, a large paver maker, puts the base at 4 to 6 in deep in its own installation guide, and installer guides commonly put driveways at 8 to 12 in. On clay, wet or weak soil, and in cold climates with hard freezes, the base needs to be thicker than any of these figures.

UseCompacted base depth
Patio or walkway4 to 6 in
Driveway8 to 12 in (6 in is the minimum on well-drained soil)
Clay, wet or weak soilDeeper than the figures above; confirm locally

Depths change with soil and use, so confirm with local guidance or a contractor before you dig. The depth box in the calculator is set from the use you pick, and you can type any depth over it.

Bedding sand is 1 in. Belgard, Unilock and the industry guide all put the bedding layer at about 1 in (about 25 mm) of coarse concrete sand, screeded level on top of the compacted base. It is a setting bed, not a levelling fix: bumps in the base show through, so the base has to be flat first.

Order extra for compaction. Loose gravel and sand settle when they are compacted, so the calculator adds 10% to the compacted volume as the default. The box is editable: on soft ground, guides suggest 15% or more.

For a 10 × 10 ft patio (100 sq ft)VolumeWith 10% compaction extra
Base, 4 in deep1.23 cubic yards1.36 cubic yards
Base, 6 in deep1.85 cubic yards2.04 cubic yards
Base, 8 in deep2.47 cubic yards2.72 cubic yards
Bedding sand, 1 in0.31 cubic yards0.34 cubic yards

Need gravel or sand for a different shape or a bigger job? The Gravel Calculator works out gravel by area and depth, and the Cubic Yard Calculator handles volumes of soil, sand and gravel in any shape.

Polymeric Sand for the Joints

When the pavers are laid, a fine sand is swept into the joints to lock them together. Polymeric sand is the modern version: it has a binder in it, and once it is swept in and misted with water it sets firm, so it stays in the joints and keeps weeds and ants out better than plain sand.

Coverage comes from the bag label, always. How much ground a bag covers depends mostly on the width of your joints and the thickness of your pavers, so makers print a coverage table on the bag instead of one number. Alliance Gator, a large maker, publishes these figures for one 50 lb bag on standard 2-3/8 in pavers:

Joint widthOne 50 lb bag covers
Narrow joints, 1/8 to 3/8 inAbout 65 to 85 sq ft
Wide joints, 3/4 to 1-1/4 inAbout 22 to 42 sq ft

The same bag covers about three times as much patio on narrow joints as on wide ones. That spread is why the calculator does not print one fixed bag count: it asks you for the coverage figure from your own bag label, and divides your area by it. It starts at 40 sq ft per bag as a cautious starting figure. Check your bag’s label and change the figure to the one printed on it before you rely on the count.

Worked with the starting figure: a 120 sq ft patio at 40 sq ft per bag needs 120 ÷ 40 = 3 bags of polymeric sand.

Edge Restraint and Spikes

A paver field slowly spreads at the edges if nothing holds it. Edge restraint is a rigid strip of plastic or metal fixed along every open edge of the job (edges against a house wall or a concrete curb do not need it), and it is pinned down with long spikes.

The length you need is the perimeter: 2 × (length + width) for a rectangle, so a 12 × 10 ft patio needs 44 linear ft of edging. A circle needs 3.1416 × the diameter.

Spikes go about every 12 to 18 in along straight runs. Brickstop, an edge restraint maker, specifies 1 spike every 16 to 20 in on patios and walkways and every 8 to 12 in on driveways and heavy load areas, with a spike at each end; installer guides put straight runs at every 12 to 18 in and closer on curves. The calculator starts at 15 in spacing and you can change it. At that spacing, 44 ft of edging takes 44 × 12 ÷ 15 = 35.2, so 36 spikes.

Excavation: How Deep to Dig

The hole has to fit every layer: the compacted base, the 1 in of bedding sand, and the paver itself. So the dig depth is base depth + 1 in + paver thickness. For the standard patio build that is 4 + 1 + 2-3/8 = 7.375 in, about 7-3/8 in. The finished pavers should end up level with, or a little above, the ground around them, and slope gently away from the house so water runs off.

The dirt that comes out is the area × the dig depth. For a 120 sq ft patio dug 7.375 in deep, that is 73.75 cu ft, or 2.73 cubic yards of dirt to move, pile or haul away. Loose dirt bulks up bigger than the hole it came from, so a trailer or dumpster fills faster than the bare figure suggests. The Cubic Yard Calculator helps with loads and truck sizes.

Before any digging, call 811. In the US this free call gets the underground utility lines on your lot marked, so you do not cut a cable or a pipe. For a driveway or anything carrying heavy loads, confirm the base depth and the drainage with local code or a professional. In freeze and thaw country, and on wet or clay soil, the base may need to be deeper than the standard figures.

Worked Example: A 12 × 10 ft Patio

Here is the full shopping list for one plain job: a 12 × 10 ft patio (120 sq ft), 6 × 9 in pavers in a straight pattern with 10% extra, a 4 in base, pavers 2-3/8 in thick, and polymeric sand at the starting coverage of 40 sq ft per bag. Every number below is what the calculator gives for these inputs:

ItemWorkingYou need
Pavers, exact120 sq ft × 2.667 per sq ft320 pavers
Pavers to buy320 + 10% extra, rounded up twice352 pavers
Base gravel, 4 in40 cu ft = 1.48 cubic yards1.63 cubic yards with 10% compaction extra
Bedding sand, 1 in10 cu ft = 0.37 cubic yards0.41 cubic yards with 10% compaction extra
Polymeric sand120 ÷ 40 sq ft per bag3 bags (50 lb)
Edge restraint2 × (12 + 10) ft44 linear ft
Edge spikes44 × 12 ÷ 15 in spacing = 35.236 spikes
Dig depth4 in base + 1 in sand + 2-3/8 in paver7.375 in (about 7-3/8 in)
Dirt to remove120 × 7.375 ÷ 12 = 73.75 cu ft2.73 cubic yards

Change any one input and the whole list moves with it: pick herringbone and the buy count rises to 368 pavers (320 with 15% extra), or pick a driveway use and the base depth jumps to 8 in.

What the Pavers Cost

Paver prices change too much from place to place and from paver to paver for any printed range to be honest, so this page prints none. Instead, type your own price into the calculator, either per paver or per sq ft, and it totals the pavers for your job:

Example only: say your paver costs $1.00 each. That is an example price to show the working, not a quote. For the patio above, 352 pavers × $1.00 = $352.00 for the pavers.

Per sq ft pricing multiplies by the area you buy (with the extra added), not just the patio area. For the same patio, the 352 pavers at 2.667 per sq ft come to 132 sq ft of pavers, so at $5 per sq ft the pavers cost $660.

That figure is the pavers only. The base gravel, bedding sand, polymeric sand and edging are extra, delivery is usually extra, and labour is not included at all. For a real number, enter the prices at your own store.

Common Mistakes

1. Rounding the paver area before you divide

A 4 × 8 in paver is 0.2222 sq ft. Round that to 0.23 sq ft before you divide, and a 600 sq ft job comes out at 2,609 pavers instead of the true 2,700, which is 91 pavers short. Keep full precision through the working and round only the final count up. This calculator, its tables and its worked example all use the same exact maths for exactly this reason.

2. Using one waste figure for every pattern

Ten percent is a fair guide for a straight pattern, but herringbone cuts on every edge and a circle cuts on the whole rim. Order a herringbone patio at the straight figure and the last rows come up short. Pick the pattern honestly, and confirm with your supplier.

3. A base that is too thin, or a driveway on a patio base

The base is what carries the load. Four inches is a patio minimum on good soil, not a driveway figure, and on clay or wet soil even a patio wants more. A thin base settles unevenly and the pavers follow it down.

4. Forgetting that loose material compacts

A cubic yard of compacted base takes more than a cubic yard of loose gravel to make. Order the exact compacted volume and the last stretch of base runs thin. The 10% compaction extra in the calculator covers the normal case; soft ground needs more.

5. Counting from a tape measure instead of the nominal size

One paver measures a little under its nominal face, because the joint takes the rest. Count with the measured size and you over-order. Count with the nominal face size, or better, with the coverage figure your maker prints.

6. Digging without checking what is buried

A patio dig is shallow, but cables and pipes can be shallow too. In the US, call 811 first and let the utility lines be marked. It is free, and it is the cheapest insurance on the whole job.

Worked example: See How Many Bricks for a 10×10 Patio? for a full patio worked out step by step, including base and sand.

Frequently Asked Questions

How many pavers do I need?

Multiply your area in square feet by the pavers per square foot for your size, then add extra for cuts for your pattern. A 10 × 10 ft patio in 4 × 8 in pavers is 100 × 4.5 = 450 pavers exactly, and 495 to buy with 10% extra on a straight pattern.

How many pavers do I need for a 12 × 10 ft patio?

It depends on the paver size. In 6 × 9 in pavers the 120 sq ft patio takes 320 pavers exactly, and 352 to buy with 10% extra. In 4 × 8 in pavers it takes 540 exactly, and 594 to buy with the same extra.

How many pavers are in a square foot?

It depends on the size: a 4 × 8 in paver gives 4.5 per sq ft, a 6 × 9 in gives 2.67, and a 12 × 12 in paver is exactly 1 per sq ft because its face is one square foot. The full chart is in the sizes section above.

How much extra should I buy for cuts?

By pattern: about 10% for a straight or running bond layout and never below 5%, about 15% for herringbone or diagonal, and 15 to 20% for curves, with 20% for a full circle. These are planning guides from installer practice, so confirm with your supplier.

How deep should the base be under pavers?

For a patio or walkway, 4 to 6 in of compacted gravel base. The industry minimum is 4 in on well-drained soil. Driveways need more: makers put them at 8 to 12 in. On clay, wet soil or in hard-freeze country, go deeper, and confirm with local guidance or a contractor.

How much sand do I need under pavers?

The bedding layer is 1 in of coarse concrete sand over the compacted base. It takes about 0.31 cubic yards per 100 sq ft, or 0.34 cubic yards with 10% extra for compaction.

How much gravel do I need under a paver patio?

At 4 in deep, about 1.23 cubic yards per 100 sq ft, or 1.36 cubic yards with 10% extra for compaction. At 6 in deep the figures are 1.85 and 2.04 cubic yards.

How many bags of polymeric sand do I need?

Divide your area by the coverage printed on your bag, because coverage swings with joint width. One maker’s 50 lb bag covers about 65 to 85 sq ft on narrow joints and only 22 to 42 sq ft on wide joints. At a coverage of 40 sq ft per bag, a 120 sq ft patio needs 3 bags.

Do I need edge restraint for pavers?

Yes, on every open edge. Without a fixed edge strip the outside pavers slowly creep outward and the joints open up. Pin the strip with spikes about every 12 to 18 in on straight runs, and closer on curves and driveways.

How deep do I dig for a paver patio?

Dig the base depth plus 1 in of bedding sand plus the paver thickness. For a standard patio that is 4 + 1 + 2-3/8 = 7.375 in, about 7-3/8 in. Call 811 before you dig so underground utility lines get marked.

About the author

Emily Jozuf is the editor at MyHomeCalculators. She tests every calculator on this site and checks the worked examples by hand, so the numbers you see are numbers you can trust for your project.

Paver counts, volumes and bag counts on this page are estimates for planning. Measure your own area before you buy, read the coverage on your own bag and pallet labels, confirm the waste with your supplier, and keep the extra for cuts and breakage.